Gas Turbine Engine Manufacturer

Gas Turbine Engine Manufacturer

GAS TURBINE ENGINE MANUFACTURER

Indianapolis, Indiana

A new test cell for development and production tests of lift fans under differing nozzle and inlet conditions. The project included a new electric utility substation to deliver 13kV power to a 40,000hp motor. Mussett Nicholas Associates was a consultant to the prime test cell facility design firm.

  • Industrial High Horsepower Test Cell
  • New Construction
  • 20,000 Square Feet

Purdue University Zucrow Lab

Purdue University Zucrow Lab

PURDUE UNIVERSITY ZUCROW LAB

West Lafayette, Indiana

Purdue University Zucrow High-Pressure Research Lab Air Heater Installation.

This project involved the installation of an air heater for the Purdue University Propulsion Lab to provide 150°F and 800 PSI compressed air for testing. The total cost of the project was $1.6 million.

  • Higher Education
  • High-Pressure Test Cell Upgrade
  • $1.6 Million